Connecting to electric networks – ask your energy carrier – light – question -answer – page 54.

Mikhail Kozyrev

Connection to electric networks Good afternoon! Please clarify. In 2015, he made a preferential TU for 550r for connecting a residential building in the garden partnership. Now in the same city I want to connect

Connection to electric networks

Good afternoon! Please clarify. In 2015, he made a preferential TU for 550r for connecting a residential building in the garden partnership. Now in the same city I want to connect an IZHS section for construction. TU came, the cost of connecting 169 thousand rubles. All neighbors have for the benefit of 550 rubles. Where did this cost come from? (U. Ufa).

Pavel · 04/22/2016 · Light / connection to electric networks · 3542 views

Mikhail Kozyrev

Hello! The fact is that in 2013 in the legislation on those. The accession to electric networks made changes according to which to connect 15 kW for 550 rubles within the same municipal district only once every three years. This was done to limit the possibility of abuse of benefits.

The norm about three years is spelled out in the rules of technological connection, paragraph 17, the fifth paragraph. Link – http://base.garant.ru/187740/

Accordingly, you need to wait for you to wait for extra money, until they expire for three years from your previous connection. Unless, of course, the situation will allow you to wait …

I have a private house in Khabarovsk. As well as its connection one phase to the network of Russian Railways. Electric circuit is installed for heating. Since the Soviet era, a 3 kW power supply distance reported. In connection with which there was a need to increase power

Alexander Barsukov · 04/22/2016 · Light / connection to electric networks · 449 views

This question is not an answer yet. If you know the answer to this question, write it!

Good afternoon. We purchased a plot, landslide lands, received TU for connecting to electric networks. And to whom to contact the pillar? And how to understand where to install this very pillar? Thank you.

Olga · 04/19/2016 · Light / Connection to electric networks · 2633 views

Specialist LLC Kronverk

Good afternoon. No one needs to contact anyone. Everything is spelled out in that.

The obligations of both yours and the network organization. If you have a distance from networks to a section of less than 500 m, then the network organization is obliged to take all measures within 6 months in order to provide your site with power supply, including Rear the line to your site and set the support.

Unfortunately, the terms of network organizations are far from always executed. After 6 months, if the work is not completed, apply with a claim, then to the court.

Vorontsov Denis, Kronverk LLC, www.kronverk.net answered the question

Pavel Subbotin

… and how to understand where to install this very pillar?

The support that the network organization is obliged should stand at a distance of not more than 25 meters from the boundaries (cadastral) of your land plot.

Next, act in accordance with paragraph 11 of the one you received.

Good afternoon, I wanted to know which electric companies belong to the power lines in the village of Shaim, the Vologda region. Since the Cherepovets networks say that they are not them, Vologdaenergo does not say their network, Opronenenergo Tlja says not their network, duck to whom to contact about the connection?

Anton · 04/19/2016 · Light / connection to electric networks · 1205 views

This question is not an answer yet. If you know the answer to this question, write it!

They purchased a premises (built until 2000) an area of ​​189 m² (non -residential, workshops and warehouse) on the territory of the former a/column. The question arose of increasing the consumption of e/energy to 15 kW. The power supply of the premises comes from the owner of the former a/column, with which the contract “for the provision of utilities and other services” is concluded. The owner refuses to provide 15 kW. What to do in this case?

Sergey · 04/18/2016 · Light / connection to electric networks · 1490 views

Victoria Grebennik

Hello, contact the network company with an application for technological connection.

Where to draw up an agreement on connecting to the electro -residents of the new house? Distance – up to 300 m, 15 kW. How much will it cost? We live LO d. Koporye Lomonosovsky district. Documents on the right of ownership and builds. There are at home. I would like to know No. tel. The mode of operation.

Nina · 04/18/2016 · Light / connection to electric networks · 1375 views

Specialist LLC Kronverk

Hello! You need to apply for technological connection at the address: St. Petersburg, ul. Red Textiler, 10-12 On working days from 9.00 to 20.00. The cost of connection in your case should be 550 rubles. Tel. 8 (800) 700-14-71

Vorontsov Denis, Kronverk LLC, www.kronverk.net answered the question

Live in a private house for two owners. The entrances to the house are from different sections of the land, each plot, like each half of the house, are privatized. There is only one wall in common. When applying for property, the addresses are indicated: house 35 kV1 and house 35 kV2. The house has two different emails from different pillars. I applied for an increase in power to 15 kV and voltage from 220V to 380V in its half of the house

Andrey · 04/18/2016 · Light / connection to electric networks · 4292 views

Specialist LLC Kronverk

If you have two apartments, then this is an apartment building. Accordingly, you must pay for the tariff as for apartment buildings.

Vorontsov Denis, Kronverk LLC, www.kronverk.net answered the question

Alexander Ivanov

What documents should I appeal to to prove that this is a separate housing?

Look. Decree of the Government of the Russian Federation of 01.28.2006 N 47. “An apartment building is recognized as a set of two or more apartments that have independent outputs either on a land plot adjacent to a residential building or to public premises in such a house. The apartment building contains elements of the common property of the owners of premises in such a house in accordance with housing legislation. ”

In order to prove your right to technological connection, it is enough for you to attach to the application of the St.and a site plan with buildings, which displays your apartment and says that The object does not have elements of common property, and therefore, according to the definition of this PP No. 47 of 01.28.2006, it is not an apartment building. An apartment building is a set of features, and not just the word apartment, which was used to refer to everything in a row during the privatization period.

PS. “If you have two apartments, then this is an apartment building” Vorontsov Denis, learn the materiel before making conclusions and taking away people's hope for a legal solution to the issue.

Our organization, which is a subscriber, has changed the point of connection with the commissioning of a new transformer substation. A transit consumer is connected to our old 0.4 kV substation, which previously fulfilled our specifications for connecting to the old substation. All our load was transferred to the new substation, while the load of the transit consumer remained at the old one

Alexander 04/17/2016 Light / Connecting to the power grid 549 views

There is no answer to this question yet. If you know the answer to this question – write it!

Received TU for connection to electric networks. There are several points in the TU that I do not understand, namely:
1. Ensuring that the impact of the Applicant's electrical installations on the quality of electricity at the point of general connection is maintained within the normally acceptable limits established by state standards and relevant technical standards. regulations

Denis · 17.04.2016 · Light / Connection to power grids · 546 views

There is no answer to this question yet. If you know the answer to this question – write it!

I am a disabled person of the 1st group after an accident, 77 years old. I am freezing in a new private house, there is no connection, Documents (technical conditions) are ready, but again sent from Anapa to Novorossiysk for signature, wait another three weeks.
Help! I can't stand it, because it's +7-10 in the house. I'm writing to you for the second time.

svetlana · 15.04.2016 · Light / Electrical connection · 657 views

There is no answer to this question yet. If you know the answer to this question – write it!

The following situation has arisen:
I am the owner of a non-residential premises located in a five-story building on the ground floor. 1.3 kW has already been received for this non-residential premises, an agreement has been signed for the supply and consumption of electricity, an act of balance ownership has been signed, we consume electricity.
1.3 kW are connected from the switchboard of a residential building (a separate cable comes from the switchboard for power supply to non-residential premises.)

There was a need to increase the electric power up to 6 kW (i.e. additionally 4.7 kW)

Natalya 04/15/2016 Light / Connecting to the power grid 2145 views

Mikhail Kozyrev

Natalia, hello. As far as I understand, you are from Ukraine. I'm afraid there are no experts familiar with the specifics of your national energy legislation on EnergoVOPROS.ru. Unfortunately ( (

Is it possible to connect 2 separate lines to one site? The house for one owner has an additional building in the form of a summer kitchen. Is it possible to draw an additional line and a separate meter?

Xenia 04/13/2016Light / connection to electric networks · 26614 views

Specialist LLC Kronverk

Hello! No. If the site is one, you can only connect to it once. If you want twice, you need to divide the site into two with different cadstrous numbers.

Vorontsov Denis, Kronverk LLC, www.kronverk.net answered the question

The voltage in the network does not exceed 130 volts. I live in a private house in the village. What to do? Where to go?

Vitaly · 04/12/2016 · Light / Connection to electric networks · 446 views

This question is not an answer yet. If you know the answer to this question, write it!

Hello, I am interested in such a question, we have technical conditions for connecting to the lines of the network company SSK, but the chairman of the country cooperative does not agree to organize the connection to the electric networks of CJSC SSK, citing a lot of space, although many neighbors will take up a lot of space We have long passed to the city line) Does it have the right to do so? We have all the technical conditions, the contract, but there is no approval with the chairman.

Daria · 04/12/2016 · Light / connection to electric networks · 2212 views

Mikhail Kozyrev

Hello! If the connection to the line of the network company is made using the infrastructure of the country cooperative, then coordination with the board is necessary. The current legislation requires in such cases when submitting an application for those. The accession to attach, among other things, an agreement with a cooperative (country partnership, partnership, etc.) to use the infrastructure, which will be involved in the course of accession.

And if there is no such contract, then the network company has the right to refuse to accept the application.

If the infrastructure (power transmission, substation) of the country cooperative is not used in connection (and such an opportunity also exists, the connection of the object in the territory of the country association can be direct, directly from the networks of the network organization), then the issue of coordination of the branch, which to It will suit you. Roughly speaking, it is necessary to go out and arrange the place of installation of the pillar (pillars) on which the line will be drawn to you. And this also rests on the chairman.

But in the second case, if you have already been issued and signed for those. Action and TU, the problem of coordination becomes the problem of the network organization. If, within the time limits established by law, the TU is not executed (from the side of the network company), you have the right to demand and insist on their implementation. And you do not make claims to your chairman, but a network company.

Previously, it was necessary to write in such cases a statement to the regional department of the FAS. Now, as I understand it, you need to contact Rospotrebnadzor.

For a network company, all this can end with serious fines. Therefore, they can, without waiting for such a development of the situation, in court to compel the rule of your cooperative to coordinate the place of placement of the pillar on which the line will be drawn to you.Moreover, the legislation will be on your (i.e., in this case, a network company) to the side. In particular, in the Rules of those. ACCESSIONS It is said that a horticultural association:

“… is not entitled to prevent the network organization in the implementation of technological accession of energy acceptance devices belonging to citizens leading gardening, gardening or summer cottage individuals individually in the territory of the gardening, garden or country non -profit association, and other persons located in the territory of this association …”

Source – “Rules for the technological connection of power receiving devices of consumers of electric energy, facilities for the production of electric energy, as well as electric grid facilities belonging to network organizations and other persons, to electric networks”, paragraph 8.5., The fourth paragraph – http: // Base. garant.ru/187740/

Although, I’m afraid that in time, this whole epic can drag on very hard … And the result is not guaranteed.